East Anglia THREE
Offshore wind farm, United Kingdom.

Tracked vessels on the farm now
No tracked vessel is on East Anglia THREE right now.
From the last three-hourly map update. Open the live map.
Vessels that built and serve it
- Wind Pace · WTIV · Cadeler
Since 2026: Turbine installation in parallel with Wind Osprey (95 Siemens Gamesa turbines); Wind Pace's first European project after delivery. Source: cadeler.com, offshorewind.biz
2023-03-29, contract: T&I of 95 turbines (shared with one O-class vessel); combined value just above EUR 100 million; work through 2026. Source: cadeler.com
- Wind Osprey · WTIV · Cadeler
Since 2026: Installed the first turbine (21 April 2026), running in parallel with Wind Pace; full T&I of 95 Siemens Gamesa turbines. Source: cadeler.com, offshorewind.biz
2023-03-29, contract: T&I of 95 wind turbines (1.4 GW), southern North Sea; scope shared with one P-class newbuild; value stated as just above EUR 100 million; work early 2026 to end 2026. Source: cadeler.com
- Seaway Moxie · other · Seaway7
Since 2026: W2W support vessel to CLV Seaway Aimery, equipment and personnel transfers. Source: offshorewind.biz
- Seaway Aimery · other · Seaway7
Since 2026: Inter-array cable installation between turbines and offshore converter platform. Source: offshorewind.biz
Detections in the last 30 days
- 7 Sept 2026WIND PACE jacked up at East Anglia Three
AIS placed WIND PACE (WTIV) at East Anglia Three for about 7 hours.